Russian Transport Ministry Outlines 100 Thousand Specialist Needs for Moscow-Petersburg High-Speed Railway
The Russian Ministry of Transport announced that over 100,000 specialists are required for the construction of the Moscow-Petersburg high-speed railway. The Ministry of Transport stated that the first construction phase of the high-speed railway requires more than 8,000 personnel. The Ministry of Transport is restructuring personnel training systems to meet the construction demands of the high-speed railway project. These announcements were made during a session on the construction of the first high-speed railway during the Transport Week.
Personnel Training Restructuring
The Ministry of Transport is restructuring personnel training systems to meet the high-speed railway construction demands. New qualifications being developed include robotic complex operators, welding specialists, and quality control experts. The Professionalitet program involves colleges and enterprises preparing personnel using unified curricula. This program aims to ensure that the workforce possesses the specific technical skills required for modern railway infrastructure development.
Ninety-five organizations will open in 42 regions in 2027 under the Professionalitet program. The Ministry of Transport plans for nearly all colleges to join the Professionalitet system by 2030. Training programs for teachers are running at the Kaluga Technopark, alongside advanced engineering schools and 11 construction and 3 railway clusters. Student detachments from 22 regions, including students from the Russian University of Transport, participated in high-speed railway construction work in the summer.
Construction Milestones Achieved
The first 700-ton bridge girder was installed in early November, manufactured at the Selinskoye testing ground. Two 900-ton transporters were used to move the girder from the production site to the installation location. The bridge structure includes 24 spans with a total mass of approximately 17,000 tons, supported by 25 piers. The installation of this girder represents a significant milestone in the ongoing construction efforts for the high-speed railway line.
The bridge structure itself is substantial, featuring 24 spans supported by 25 piers. The total mass of the bridge structure is approximately 17,000 tons. The installation of the first 700-ton bridge girder in early November marked a critical progress point for the project. This girder was manufactured at the Selinskoye testing ground before being transported to the installation site.
Project Timeline and Testing
Train testing for the high-speed railway is scheduled to begin in the summer of 2027. The overall project is planned for completion by 2028. The Ministry of Transport stated that over 100,000 specialists are required for the entire high-speed railway project. These figures underscore the massive scale of the infrastructure development underway across the Russian Federation.
The Ministry of Transport announced these figures during a session on the construction of the first high-speed railway during the Transport Week. The Minister of Transport stated that over 100,000 specialists are needed for the entire high-speed railway project, leading to the creation of a specialized high-speed movement engineer specialty in transport universities. The government continues to emphasize the importance of specialized workforce development to meet these ambitious construction timelines.